Case Studies
Insights from real projects that tell our story
Case Study 1
New Pet Clinic – California
Project Overview
Project Type: Veterinary Clinic (New Construction)
Location: California
Service Provided: Code-Compliant Building Trade Review
Challenge
Prior to permit submission, the design team requested an independent code review to identify potential compliance issues that could result in permit comments, redesigns, or project delays.
Our Review
Codexperts LLC conducted a comprehensive code compliance review of the architectural and building systems documentation.
Key Findings
A total of 29 code-related deficiencies were identified, including:
Egress and Life Safety
Excessive travel distances
Occupant load calculation discrepancies
Exit access concerns
Accessibility (ADA)
Insufficient clear floor space at accessible elements
Accessible parking compliance concerns
Maneuvering clearance deficiencies
Code Documentation
Missing or incorrect code references
Inconsistent code analysis information
Trade Coordination
Architectural and MEP coordination conflicts
Building system interactions affecting code compliance
Result
The design team was able to address identified issues before permit submission, reducing the likelihood of permit comments and minimizing potential redesign efforts during the review process.
Value Delivered
✓ 29 compliance issues identified before submission
✓ Reduced permit review risk
✓ Improved coordination between disciplines
✓ Increased confidence in the final permit package
Case Study 2
Office Building – New Jersey
Project Overview
Project Type: Office Building
Location: New Jersey
Service Provided: Code-Compliant Building Trade Review
Challenge
The project involved multiple disciplines and complex life-safety requirements. The design team sought an independent review to verify compliance before submitting construction documents for permit.
Our Review
Codexperts LLC performed a detailed code and constructability review focused on life safety, accessibility, and inter-disciplinary coordination.
Key Findings
A total of 38 code-related deficiencies were identified.
Egress and Life Safety
Travel distance deficiencies
Occupant load calculation discrepancies
Exit arrangement concerns
Accessibility (ADA)
Clear floor area deficiencies
Door maneuvering and access issues
Accessible route concerns
Fire-Resistance-Rated Construction
Fire barrier separation deficiencies
Improper penetration protection details
Stair shaft enclosure concerns
Code Documentation
Incorrect or incomplete code references
Inconsistencies between drawings and code analysis
Trade Coordination
Architectural, mechanical, electrical, and plumbing conflicts
Design elements affecting life-safety systems
Result
By identifying critical deficiencies before submission, the design team was able to make corrections during design rather than during permit review or construction.
Value Delivered
✓ 38 code issues identified before permitting
✓ Reduced risk of permit review comments
✓ Improved fire-resistance-rated assembly compliance
✓ Enhanced coordination between design disciplines
✓ Reduced potential construction change orders
Case Study 3
Church Addition – North Carolina
Project Overview
Project Type: Church Addition
Location: North Carolina
Service Provided: Code Research and Feasibility Analysis
Challenge
The project team needed to determine whether the proposed addition would trigger:
Installation of an NFPA 13 automatic sprinkler system
Additional plumbing fixture requirements
Both requirements had the potential to significantly increase project costs.
Our Analysis
Codexperts LLC conducted a detailed code analysis of:
Building area and occupancy classifications
Existing building provisions
Sprinkler thresholds
Plumbing fixture calculations
Applicable North Carolina code requirements
Findings
Through a comprehensive review of applicable code provisions, we determined that:
The proposed addition could proceed without triggering a new NFPA 13 sprinkler system requirement.
Existing restroom fixture counts remained compliant and additional fixtures were not required.
Result
The owner and design team were able to move forward with the project while avoiding significant construction costs associated with sprinkler installation and restroom expansion. The project passed the local jurisdiction review during the first review cycle and moved the project from design to construction several weeks ahead of schedule.
Value Delivered
✓ Confirmed project feasibility early in design
✓ Avoided unnecessary sprinkler system installation costs
✓ Avoided additional restroom construction costs
✓ Provided documented code justification for design decisions
✓ Supported informed project budgeting and planning
Consulting
Efficient building code review services nationwide.
Contact information
info@codexperts.com
704-750-CODE
© 2026. All rights reserved.